Survey Project Details

Project Information
SGB Project Number 201917122 Status Closed
Client/Surveyor Project Number 37616 Faro Explanatory Plan (Transmission Line)
Description Covers a short reroute of the line: EXPLANATORY PLAN OF RELOCATION OF PART OF TRANSMISSION LINE RIGHT-OF-WAY FROM CONGLOMERATE MOUNTAIN TO VANGORDA
Canada Land(s) QUAD 105K/06 (105K/06) Surveyor BURBIDGE, PAUL ANDREW (opens in new window)
First Nation
Province / Territory YUKON (YT)
Company CHALLENGER GEOMATICS LTD.
Survey Plan Type Explanatory Plan Contract Number
Date Opened 2019-10-08 Date Closed 2020-02-28
Survey Instructions
Instructions Requested on 2019-10-09
Instructions Issued on 2019-10-10
Survey Document: #50778
Survey Document Name EXPLANATORY PLAN OF RELOCATION OF PART OF TRANSMISSION LINE RIGHT-OF-WAY FROM CONGLOMERATE MOUNTAIN TO VANGORDA
Survey Document Type Explanatory Plan
Checklist Number 7033
Signed Returns Received by SGB 2019-11-08
Outstanding Critical Issue No
Final Returns Received 2019-11-08
eApprovals
Agency Initiated Received Status
Yukon Land Planning 2019-11-18 2019-11-20 Approved
Surveyor General Approved / Confirmed 2019-11-20
CLSR Number 108750 CLSR YT
Plan Image Uploaded 2020-11-06
Datasets Updated 2019-12-23
LTO Number