Project Information
| SGB Project Number | 201317112 | Status | Closed |
|---|---|---|---|
| Client/Surveyor Project Number | 36592 | ||
| Description | Explanatory Plan of Pelly Crossing to Stewart Crossing Transmission Line Right-of-Way | ||
| Canada Land(s) |
QUAD 115I/15 (115I/15) QUAD 115I/16 (115I/16) QUAD 115P/01 (115P/01) |
Surveyor | ILES, JOE C. (opens in new window) |
| First Nation | |||
| Province / Territory |
YUKON (YT) |
Company | CHALLENGER GEOMATICS LTD. |
| Survey Plan Type | CLS Act survey of parcels within Yukon settlement land | Contract Number | |
| Date Opened | 2013-12-11 | Date Closed | 2018-08-14 |
Survey Instructions
| Instructions Requested on | 2013-12-11 |
|---|---|
| Instructions Issued on | 2013-12-17 |
Survey Document: #47201
| Survey Document Name | The Pelly Crossing to Stewart Crossing transmission Line Right-of-Way |
|---|---|
| Survey Document Type | Partial Survey |
| Checklist Number | 5045 |
| Signed Returns Received by SGB | 2017-12-14 |
| Outstanding Critical Issue | No |
| Final Returns Received | 2017-12-14 |
| Surveyor General Approved / Confirmed | 2018-06-08 |
| CLSR Number | 107249 CLSR YT |
| Plan Image Uploaded | 2019-06-25 |
| Datasets Updated | 2018-08-02 |
| LTO Number |